Specialists of the External Works Service of INGC LLC have started a final stage of the installation supervision at two gas pumping units of “Irtysh” series manufactured in 2023 at the company’s plant in Perm for the facilities of Uzbekneftegaz JSC.
- two sets of “Irtysh” GPU-16 for “Surgil” BCS driven by Nova LT16 gas turbine engine (by Baker Hughes) and 2ВCL608 centrifugal compressor (by Baker Hughes).
The specialists of INGC Design Bureau have developed design and technical documentation and at INGC production site in Perm, they manufactured, assembled and shipped two complete GPU-16 units of “Irtysh” series.
At the moment, installation of the main process equipment: compressor unit, engine unit as well as installation of a hangar shelter, inlet air filter unit, etc. has been completed at the construction facility of “Surgil” BCS in Uzbekistan. The units are of high degree of preparation for the commissioning.